The steel erection of the new building was completed last week! In the days that followed this, there was additional welding and plumbing up of the columns and the Mechanical/Electrical/Plumbing (MEP) rough-ins under the slab for the Commons Area were finished. This week we have been watching work progress on the site, including Mechanical/Electrical/Plumbing (MEP) rough-ins under the slab for the Sanctuary, and MEP rough-ins for 2nd Floor of the Commons Area. The concrete slab is being poured on grade for the Commons Area. After this is poured, the concrete floor slab for the 2nd floor Commons Area will be done.
And finally, here's one last picture taken this afternoon: You can see the roof trusses are starting to be installed!